Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the wordpress-seo domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /nas/content/live/illong/wp-includes/functions.php on line 6114
WFU McCreary Field House - I.L. Long Construction Co., Inc
Project Location

Winston-Salem, NC

Square Footage

89,290

Schedule Duration

14 months

Scope

McCreary Field House is a new indoor practice facility that incorporates a full (120 Yd.) football field with the same specifications and design as the exterior fields used for competition. The facility is approximately 400’ x 200’ with a 72’ ridge height. The facility is located in the center of campus and required the relocation 80,000 CY of soil with 40,000 CY being exported from the campus. All utility work was completed without impacting campus operations and incorporated seven day windows for connections and planned shutdowns in both June and December.

Highlights

Highlights include a player’s locker room, overhead glass doors that allow quick access from the indoor field to exterior practice fields, elevated film platforms, exterior balcony and translucent wall panels.

This project achieved LEED Silver Certification.