Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the wordpress-seo domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /nas/content/live/illong/wp-includes/functions.php on line 6114
Jerry Long YMCA - I.L. Long Construction Co., Inc
Project Location

Clemmons, NC

Square Footage

10,790

Schedule Duration

11 months

Scope

The project consists of a new indoor pool addition which encloses a warm water L-shaped pool with swimming lanes and a connected zero entry. A separate 1,445 SF Teen Room addition was constructed on the back side of the existing building. The new additions were constructed with CMU and a brick veneer to match the existing building.

 

Highlights

Highlights includes all new pool equipment and a new dehumidification system to improve air quality in the pool.